Italian gasfield approved for Po Valley Ltd

24 June 2008 | 04:52 Code : 17611 Geoscience events
visits:58
The environmental approval for a second gasfield in northern Italy being...

  The environmental approval for a second gasfield in northern Italy being developed by Australia’s Po Valley Ltd has been granted.The decision by the Lombardia Region authorities to approve Po Valley Energy’s Castello gasfield near Milan follows environment approval for the Company’s Sillaro field near Bologna approved on 21 January 2008.Both fields will host Po Valley’s maiden production which, subject to remaining approval processes, is expected by the Company towards the end of 2008.The funding required to bring the Sillaro and Castello fields into production, including a second production well in the Sillaro field, is in place with the recently completed $34 million reservoir financing facility with the Bank of Scotland.Po Valley said today that the surface plant construction and grid connection infrastructure works continued to advance for both projects.“Construction of the key surface plant equipment for both fields is more than 30% complete and the equipment mounted skids are on schedule and will be assembled and tested at the facility of the manufacturer, Semat, in June” CEO, Michael Masterman said today.“The pipeline operator, SNAM Rete Gas (SRG), has advised that it is similarly advanced in its preparations to install pipeline grid connections to both Sillaro and Castello”, Mr. Masterman said.“Gas production, based on our current civil works and installation plans, can be achieved about 4 months from regulatory approval for site access, subject always to weather conditions.“While we hope to receive final concession grant for Sillaro by May 2008, our plans allow up to a further 3 months for the Ministry office in Bologna to approve the development plan and associated site access documentation. This should permit gas production by December 2008.Production at Castello is targetted to commence about 2 months later. The Italian election on 13–14 April may cause these target dates to extend by a further 2 months.”“We are one of the first companies set to be granted new gas production concessions in Italy since the deregulation of the Po River Valley region and introduction of the new approval process under the 2004 “Marzano” energy law.In preparation for maiden gas production, the Company has commenced its gas marketing program. In January, the Company briefed 13 prospective customers in Milan and 10 have requested follow up meetings. The Company plans to finalise contractual arrangements in June 2008.


Your Comment :