Golden Star Resources has completed all the mitigation work required by the Ghana Environmental

06 February 2012 | 15:59 Code : 6109 Geoscience events
visits:225
Golden Star Resources has completed all the mitigation work required by the Ghana Environmental ...
Golden Star Resources has completed all the mitigation work required by the Ghana Environmental Protection Agency at the Plant-North pit of its Bogoso/ Prestea mine in Ghana.
Mining at the Plant-North pit, the source of ore for the Bogoso plant, was suspended on September 28 pending the completion of certain mitigation measures including relocation of the Prestea police to a new station, fence erection around the Phase 3 pit development, bypass road construction to divert traffic, among others. While pit operations are suspended, the plant has continued its full production using stockpiled ore. The agency is scheduled to review the completed mitigation measures around October 18 and mining will restart thereafter.